The Valley - Avena 2photo: emaar.comUnder construction

The Valley - Avena 2

DLD project no. 3159 · Al Yufrah 1

Progress
42.89%
DLD inspected 20 Jul 2026
Handover
~ Jul 2028
Est. finish 31 Jul 2028
Escrow
#0205345068523
Registered escrow account
Google rating
5.0 ★
1 reviews

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
42.89% of construction complete · last inspected by DLD 20 Jul 2026

on pace — ≈7 pts behind the plan as of the last inspection

today
inspected 20 Jul 2026
start 23 Jul 2024 est. finish 31 Jul 2028
Google · this project
5.0
1 reviews

Location

The Valley - Avena 2: common questions

Is The Valley - Avena 2 delayed?

Not by DLD figures. Construction was 42.89% complete at the last DLD inspection on 20 July 2026, in line with or ahead of its registered timeline (about 49% expected by then, planned completion 31 July 2028).

When is the handover of The Valley - Avena 2?

The planned completion date registered with Dubai Land Department is 31 July 2028. Handover usually follows completion; the developer confirms the exact date.

How much of The Valley - Avena 2 is built?

Construction was 42.89% complete at the last DLD inspection on 20 July 2026, as published by Dubai Land Department.

Where is The Valley - Avena 2 located?

The Valley - Avena 2 is in Al Yufrah 1, Dubai.

Does The Valley - Avena 2 have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205345068523. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in The Valley - Avena 2?

The most recent sale registered with Dubai Land Department was on 16 October 2026 for AED 4,577,888. Across the 3 recorded sales, the average was AED 1,181 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.