The Valley - Avenaphoto: emaar.comActive
Progress
24.47%
Handover
~ Jun 2028
Escrow
#3538215410314

The Valley - Avena

#3158 · EMAAR DEVELOPMENT P.J.S.C. · Al Yufrah 1

More from Emaar
data last checked 17 Jul 2026

Construction progress

24.47% of construction complete · last inspected by DLD 16 Jun 2026

on pace — ≈25 pts behind the plan as of the last inspection

today
inspected 16 Jun 2026
start 23 Jun 2024 est. finish 30 Jun 2028