THE RINGSphoto: pmrproperty.comDelayed 10 mo.

THE RINGS

DLD project no. 2767 · Jumeirah Second

Progress
35.07%
DLD inspected 26 Aug 2026
Handover
Overdue
Planned finish 25 Dec 2025
Escrow
#1008014829
Registered escrow account
Google rating
5.0 ★
4 reviews

Developer: P M R Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
35.07% of construction complete · last inspected by DLD 26 Aug 2026

overdue — planned finish was 25 Dec 2025, still at 35.07%

today
inspected 26 Aug 2026
start 20 Jan 2024 est. finish 25 Dec 2025
Google · this project
5.0
4 reviews

Location

THE RINGS: common questions

Is THE RINGS delayed?

Yes. Its planned completion date registered with Dubai Land Department was 25 December 2025, and at the last DLD inspection on 26 August 2026 construction was 35.07% complete.

When is the handover of THE RINGS?

The planned completion date registered with Dubai Land Department is 25 December 2025. That date has passed and construction is still under way, so confirm the current schedule with the developer.

How much of THE RINGS is built?

Construction was 35.07% complete at the last DLD inspection on 26 August 2026, as published by Dubai Land Department.

Where is THE RINGS located?

THE RINGS is in Jumeirah Second, Dubai.

Who is the developer of THE RINGS?

THE RINGS is developed by P M R Development L.L.C. It is registered with Dubai Land Department as project no. 2767.

Does THE RINGS have an escrow account?

Yes. Dubai Land Department open data lists escrow account 1008014829. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in THE RINGS?

The most recent sale registered with Dubai Land Department was on 15 July 2026 for AED 65,000,000. Across the 1 recorded sales, the average was AED 7,639 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.