photo: theorchardplace.aeDelayed 2 mo.The Orchard Place
DLD developer no. 1476 · PEAK SUMMIT REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
RESIDENTIAL TOWERS G+4P+2TOWERS (23F+30F) + ROOF.The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 15 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 73.02 | 786 | 1,050,000.58 | 14,380 | 1,336 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 2 B/R | 120.6 | 1,298 | 1,710,000.67 | 14,179 | 1,317 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 74.28 | 800 | 1,070,000.43 | 14,405 | 1,338 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · Studio | 48.36 | 521 | 720,000.61 | 14,888 | 1,383 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · Studio | 49.91 | 537 | 740,000.6 | 14,827 | 1,377 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 66.97 | 721 | 980,000.81 | 14,633 | 1,359 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 66.85 | 720 | 960,000.76 | 14,361 | 1,334 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 2 B/R | 93.64 | 1,008 | 1,330,000.76 | 14,203 | 1,320 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · Studio | 49.18 | 529 | 730,000.38 | 14,843 | 1,379 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 73.02 | 786 | 1,050,000.58 | 14,380 | 1,336 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · Studio | 49.18 | 529 | 730,000.38 | 14,843 | 1,379 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 74.28 | 800 | 1,070,000.43 | 14,405 | 1,338 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 2 B/R | 120.6 | 1,298 | 1,710,000.67 | 14,179 | 1,317 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · 2 B/R | 93.64 | 1,008 | 1,330,000.76 | 14,203 | 1,320 |
| 15 Sept 2026 | Gifts | Off-plan | Flat · Studio | 48.36 | 521 | 720,000.61 | 14,888 | 1,383 |
The Orchard Place: common questions
Is The Orchard Place delayed?
It is behind plan. Construction was 42.68% complete at the last DLD inspection on 13 April 2026, while its registered timeline (planned completion 31 July 2026) would expect about 90% by then.
When is the handover of The Orchard Place?
The planned completion date registered with Dubai Land Department is 31 July 2026. Handover usually follows completion; the developer confirms the exact date.
How much of The Orchard Place is built?
Construction was 42.68% complete at the last DLD inspection on 13 April 2026, as published by Dubai Land Department.
Where is The Orchard Place located?
The Orchard Place is in Jumeirah Village Circle (JVC), Dubai. Dubai Land Department records it under the Al Barsha South Fourth area.
Who is the developer of The Orchard Place?
The Orchard Place is developed by PEAK SUMMIT REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1476). It is registered with Dubai Land Department as project no. 2629, with 418 units.
Does The Orchard Place have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1011225707918003. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in The Orchard Place?
The most recent sale registered with Dubai Land Department was on 18 June 2026 for AED 4,687,500. Across the 12 recorded sales, the average was AED 1,462 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.