photo: ellingtonproperties.aeUnder constructionDLD developer no. 1117 · ELLINGTON PROPERTIES DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Ellington →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Gifts | Off-plan | Flat · 2 B/R | 111.16 | 1,197 | 2,010,153.6 | 18,083 | 1,680 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 44.56 | 480 | 923,828 | 20,732 | 1,926 |
| 19 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 72.12 | 776 | 1,307,828 | 18,134 | 1,685 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 115.78 | 1,246 | 1,937,828 | 16,737 | 1,555 |
| 7 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 115.98 | 1,248 | 2,055,828 | 17,726 | 1,647 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 111.16 | 1,197 | 2,020,828 | 18,179 | 1,689 |
| 30 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.88 | 784 | 1,482,828 | 20,346 | 1,890 |
| 30 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 115.78 | 1,246 | 2,111,828 | 18,240 | 1,695 |
| 29 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 111.16 | 1,197 | 2,000,828 | 18,000 | 1,672 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.34 | 779 | 1,355,828 | 18,742 | 1,741 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.12 | 776 | 1,469,828 | 20,380 | 1,893 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.34 | 779 | 1,299,828 | 17,968 | 1,669 |
| 15 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 71.91 | 774 | 1,469,828 | 20,440 | 1,899 |
| 15 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.34 | 779 | 1,387,828 | 19,185 | 1,782 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 72.34 | 779 | 1,268,828 | 17,540 | 1,630 |
THE HILLGATE: common questions
Is THE HILLGATE delayed?
It is behind plan. Construction was 3.12% complete at the last DLD inspection on 4 June 2026, while its registered timeline (planned completion 30 June 2028) would expect about 38% by then.
When is the handover of THE HILLGATE?
The planned completion date registered with Dubai Land Department is 30 June 2028. Handover usually follows completion; the developer confirms the exact date.
How much of THE HILLGATE is built?
Construction was 3.12% complete at the last DLD inspection on 4 June 2026, as published by Dubai Land Department.
Where is THE HILLGATE located?
THE HILLGATE is in Silicon Oasis (DSO), Dubai.
Who is the developer of THE HILLGATE?
THE HILLGATE is developed by ELLINGTON PROPERTIES DEVELOPMENT L.L.C (DLD developer no. 1117). It is registered with Dubai Land Department as project no. 3594.
Does THE HILLGATE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 4031224708340005. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in THE HILLGATE?
The most recent sale registered with Dubai Land Department was on 20 October 2026 for AED 923,828. Across the 149 recorded sales, the average was AED 1,650 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.