The Haven IIIphoto: merakidevelopers.comActive
Progress
6.17%
Handover
~ Dec 2027
Escrow
#001582195397301

The Haven III

#3876 · MERAKI REAL ESTATE DEVELOPMENT L.L.C · Majan

data last checked 17 Jul 2026

Construction progress

6.17% of construction complete · last inspected by DLD 5 Aug 2026

≈36 pts behind the planned pace as of the last inspection

today
inspected 5 Aug 2026
start 1 Aug 2025 est. finish 31 Dec 2027