photo: bolddeveloper.comUnder constructionThe Collective
Developer: Bold Living Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 15 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 99.08 | 1,066 | 2,025,000 | 20,438 | 1,899 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 63.15 | 680 | 898,000 | 14,220 | 1,321 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 101.43 | 1,092 | 1,760,000 | 17,352 | 1,612 |
| 30 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 93.27 | 1,004 | 1,350,000 | 14,474 | 1,345 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 99.67 | 1,073 | 1,495,000 | 14,999 | 1,394 |
| 20 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 63.15 | 680 | 874,200 | 13,843 | 1,286 |
| 21 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 65.1 | 701 | 925,000 | 14,209 | 1,320 |
| 21 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 99.53 | 1,071 | 2,020,000 | 20,295 | 1,886 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 93.27 | 1,004 | 1,512,000 | 16,211 | 1,506 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 76.44 | 823 | 1,137,600 | 14,882 | 1,383 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 99.53 | 1,071 | 1,435,200 | 14,420 | 1,340 |
| 4 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 101.45 | 1,092 | 2,025,000 | 19,961 | 1,854 |
| 2 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 63.15 | 680 | 880,000 | 13,935 | 1,295 |
| 5 May 2026 | Sales | Off-plan | Flat · 1 B/R | 79.28 | 853 | 1,033,000 | 13,030 | 1,211 |
| 22 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 93.28 | 1,004 | 1,450,000 | 15,545 | 1,444 |
The Collective: common questions
Is The Collective delayed?
It is behind plan. Construction was 5.71% complete at the last DLD inspection on 20 August 2026, while its registered timeline (planned completion 31 March 2028) would expect about 39% by then.
When is the handover of The Collective?
The planned completion date registered with Dubai Land Department is 31 March 2028. Handover usually follows completion; the developer confirms the exact date.
How much of The Collective is built?
Construction was 5.71% complete at the last DLD inspection on 20 August 2026, as published by Dubai Land Department.
Where is The Collective located?
The Collective is in Madinat Al Mataar, Dubai.
Who is the developer of The Collective?
The Collective is developed by Bold Living Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3888.
Does The Collective have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3718501423203. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in The Collective?
The most recent sale registered with Dubai Land Department was on 15 October 2026 for AED 2,025,000. Across the 48 recorded sales, the average was AED 1,354 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.