photo: albarari.comUnder constructionTHE CAPE
DLD developer no. 1740 · BARARI THREE REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Residential building (2B+G+8+Roof) on Plot no. 645-3379 at Albarari, wadi al safa 3, Dubai-UAE
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 113.19 | 1,218 | 3,538,061 | 31,258 | 2,904 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 224.79 | 2,420 | 6,421,278 | 28,566 | 2,654 |
| 7 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 112.18 | 1,207 | 3,340,784 | 29,781 | 2,767 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 112.84 | 1,215 | 3,227,554 | 28,603 | 2,657 |
| 10 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 170.92 | 1,840 | 5,099,500 | 29,836 | 2,772 |
| 9 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 165.14 | 1,778 | 5,047,588 | 30,566 | 2,840 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 199.71 | 2,150 | 6,762,797 | 33,863 | 3,146 |
| 20 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 113.13 | 1,218 | 3,444,216 | 30,445 | 2,828 |
| 14 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 113.13 | 1,218 | 3,575,000 | 31,601 | 2,936 |
| 10 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 300.27 | 3,232 | 8,580,914 | 28,577 | 2,655 |
| 7 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 169.3 | 1,822 | 5,368,741 | 31,711 | 2,946 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 191.06 | 2,057 | 5,844,281 | 30,589 | 2,842 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 202.84 | 2,183 | 6,650,000 | 32,784 | 3,046 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 199.61 | 2,149 | 6,347,715 | 31,801 | 2,954 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 3 B/R | 258.05 | 2,778 | 8,070,526 | 31,275 | 2,906 |
THE CAPE: common questions
Is THE CAPE delayed?
Not by DLD figures. Construction was 0.71% complete at the last DLD inspection on 2 July 2026, in line with or ahead of its registered timeline (about 16% expected by then, planned completion 31 December 2028).
When is the handover of THE CAPE?
The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of THE CAPE is built?
Construction was 0.71% complete at the last DLD inspection on 2 July 2026, as published by Dubai Land Department.
Where is THE CAPE located?
THE CAPE is in Al Barari, Dubai. Dubai Land Department records it under the Wadi Al Safa 3 area.
Who is the developer of THE CAPE?
THE CAPE is developed by BARARI THREE REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1740). It is registered with Dubai Land Department as project no. 4258, with 288 units.
Does THE CAPE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0323632507002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in THE CAPE?
The most recent sale registered with Dubai Land Department was on 21 October 2026 for AED 3,538,061. Across the 126 recorded sales, the average was AED 2,926 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.