photo: object-1.comUnder constructionTetris Tower
DLD developer no. 2203 · LE LUMINOUS REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Ground+3 podiums+16 recurring residential floors
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 71.16 | 766 | 1,160,314 | 16,306 | 1,515 |
| 27 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.99 | 430 | 701,468 | 17,541 | 1,630 |
| 20 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 69.79 | 751 | 1,189,600 | 17,045 | 1,584 |
| 19 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.74 | 428 | 735,120 | 18,498 | 1,719 |
| 15 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 111.31 | 1,198 | 1,699,420 | 15,267 | 1,418 |
| 15 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.98 | 430 | 694,579 | 17,373 | 1,614 |
| 15 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 113.96 | 1,227 | 1,577,159 | 13,840 | 1,286 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 41.01 | 441 | 728,204 | 17,757 | 1,650 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 69.79 | 751 | 1,199,593 | 17,189 | 1,597 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 113.96 | 1,227 | 1,941,383 | 17,036 | 1,583 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 38.38 | 413 | 664,101 | 17,303 | 1,608 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.02 | 452 | 635,212 | 15,117 | 1,404 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.32 | 456 | 723,176 | 17,088 | 1,588 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.99 | 430 | 842,110 | 21,058 | 1,956 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 111.31 | 1,198 | 1,738,350 | 15,617 | 1,451 |
Tetris Tower: common questions
Is Tetris Tower delayed?
It is behind plan. Construction was 8.08% complete at the last DLD inspection on 30 July 2026, while its registered timeline (planned completion 30 September 2027) would expect about 52% by then.
When is the handover of Tetris Tower?
The planned completion date registered with Dubai Land Department is 30 September 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Tetris Tower is built?
Construction was 8.08% complete at the last DLD inspection on 30 July 2026, as published by Dubai Land Department.
Where is Tetris Tower located?
Tetris Tower is in Jumeirah Village Circle (JVC), Dubai. Dubai Land Department records it under the Al Barsha South Fourth area.
Who is the developer of Tetris Tower?
Tetris Tower is developed by LE LUMINOUS REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2203). It is registered with Dubai Land Department as project no. 3646, with 205 units.
Does Tetris Tower have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000892. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Tetris Tower?
The most recent sale registered with Dubai Land Department was on 28 October 2026 for AED 1,160,314. Across the 37 recorded sales, the average was AED 1,608 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.