photo: almizan.comUnder constructionTERVA HOMES
DLD developer no. 1931 · RDG PROPERTY DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
24 nos villa (G+1F+R)
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
No sales match this filter in the stored window.
TERVA HOMES: common questions
Is TERVA HOMES delayed?
It is behind plan. Construction was 16% complete at the last DLD inspection on 14 July 2026, while its registered timeline (planned completion 2 May 2027) would expect about 49% by then.
When is the handover of TERVA HOMES?
The planned completion date registered with Dubai Land Department is 2 May 2027. Handover usually follows completion; the developer confirms the exact date.
How much of TERVA HOMES is built?
Construction was 16% complete at the last DLD inspection on 14 July 2026, as published by Dubai Land Department.
Where is TERVA HOMES located?
TERVA HOMES is in Saih Shuaib 2, Dubai.
Who is the developer of TERVA HOMES?
TERVA HOMES is developed by RDG PROPERTY DEVELOPMENT L.L.C (DLD developer no. 1931). It is registered with Dubai Land Department as project no. 4231, with 24 units.
Does TERVA HOMES have an escrow account?
Yes. Dubai Land Department open data lists escrow account 90030200025685. Always confirm the account with the developer or in the Dubai REST app before paying.
Answers are generated from Dubai Land Department open data shown on this page.