Terra Towerphoto: dugasta.comActive
Progress
7.43%
Handover
~ Apr 2027
Escrow
#019000084928

Terra Tower

#3278 · DUGASTA PROPERTIES DEVELOPMENT L.L.C · Dubai Land Residence Complex

data last checked 17 Jul 2026

Construction progress

7.43% of construction complete · last inspected by DLD 8 Jul 2026

≈60 pts behind the planned pace as of the last inspection

today
inspected 8 Jul 2026
start 1 Nov 2024 est. finish 30 Apr 2027