Terra Heightsphoto: emaar.comUnder construction

Terra Heights

DLD project no. 3381 · Dubai South

Progress
9.11%
DLD inspected 31 Jul 2026
Handover
~ Mar 2029
Est. finish 31 Mar 2029
Escrow
#001582136161501
Registered escrow account
Google rating
5.0 ★
3 reviews

DLD developer no. 1237 · DWTC EMAAR L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Emaar →
DLDConstruction inspection
9.11% of construction complete · last inspected by DLD 31 Jul 2026

on pace — ≈24 pts behind the plan as of the last inspection

today
inspected 31 Jul 2026
start 10 Apr 2025 est. finish 31 Mar 2029
Google · this project
5.0
3 reviews

Location

Terra Heights: common questions

Is Terra Heights delayed?

Not by DLD figures. Construction was 9.11% complete at the last DLD inspection on 31 July 2026, in line with or ahead of its registered timeline (about 33% expected by then, planned completion 31 March 2029).

When is the handover of Terra Heights?

The planned completion date registered with Dubai Land Department is 31 March 2029. Handover usually follows completion; the developer confirms the exact date.

How much of Terra Heights is built?

Construction was 9.11% complete at the last DLD inspection on 31 July 2026, as published by Dubai Land Department.

Where is Terra Heights located?

Terra Heights is in Dubai South, Dubai.

Who is the developer of Terra Heights?

Terra Heights is developed by DWTC EMAAR L.L.C (DLD developer no. 1237). It is registered with Dubai Land Department as project no. 3381.

Does Terra Heights have an escrow account?

Yes. Dubai Land Department open data lists escrow account 001582136161501. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Terra Heights?

The most recent sale registered with Dubai Land Department was on 23 October 2026 for AED 2,139,888. Across the 18 recorded sales, the average was AED 1,975 per sq ft.