photo: tarafholding.comUnder constructionTerra Golf Collection
DLD developer no. 1549 · TARAF DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 14 Jul 2026 | Sales | Off-plan | Villa · 6 B/R | 226.58 | 2,439 | 10,950,000 | 48,327 | 4,490 |
| 1 Jul 2026 | Sales | Off-plan | Villa · 6 B/R | 380 | 4,090 | 17,910,000 | 47,132 | 4,379 |
| 21 May 2026 | Sales | Off-plan | Villa · 6 B/R | 490 | 5,274 | 14,992,000 | 30,596 | 2,842 |
| 6 May 2026 | Sales | Ready | Residential | 312 | 3,358 | 14,740,000 | 47,244 | 4,389 |
| 20 Apr 2026 | Sales | Off-plan | Villa · 6 B/R | 441.52 | 4,752 | 21,100,000 | 47,789 | 4,440 |
| 7 Apr 2026 | Sales | Off-plan | Villa · 6 B/R | 226.58 | 2,439 | 10,605,000 | 46,805 | 4,348 |
| 7 Apr 2026 | Sales | Off-plan | Villa · 6 B/R | 330.01 | 3,552 | 14,797,000 | 44,838 | 4,166 |
| 6 Apr 2026 | Sales | Off-plan | Villa · 6 B/R | 380 | 4,090 | 17,910,000 | 47,132 | 4,379 |
| 30 Mar 2026 | Sales | Off-plan | Villa · 6 B/R | 226.58 | 2,439 | 10,605,000 | 46,805 | 4,348 |
| 9 Mar 2026 | Sales | Off-plan | Villa · 6 B/R | 434.59 | 4,678 | 20,249,000 | 46,593 | 4,329 |
| 9 Mar 2026 | Sales | Off-plan | Villa · 6 B/R | 380 | 4,090 | 17,910,000 | 47,132 | 4,379 |
| 12 Feb 2026 | Sales | Off-plan | Villa · 6 B/R | 300.78 | 3,238 | 8,365,000 | 27,811 | 2,584 |
| 4 Feb 2026 | Sales | Off-plan | Villa · 6 B/R | 295.23 | 3,178 | 7,350,000 | 24,896 | 2,313 |
| 30 Jan 2026 | Sales | Off-plan | Villa · 6 B/R | 226.58 | 2,439 | 10,605,000 | 46,805 | 4,348 |
| 22 Jan 2026 | Sales | Off-plan | Villa · 6 B/R | 226.58 | 2,439 | 10,605,000 | 46,805 | 4,348 |
Terra Golf Collection: common questions
Is Terra Golf Collection delayed?
It is behind plan. Construction was 20.05% complete at the last DLD inspection on 1 September 2026, while its registered timeline (planned completion 31 December 2027) would expect about 65% by then.
When is the handover of Terra Golf Collection?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Terra Golf Collection is built?
Construction was 20.05% complete at the last DLD inspection on 1 September 2026, as published by Dubai Land Department.
Where is Terra Golf Collection located?
Terra Golf Collection is in Me'Aisem First, Dubai.
Who is the developer of Terra Golf Collection?
Terra Golf Collection is developed by TARAF DEVELOPMENT L.L.C (DLD developer no. 1549). It is registered with Dubai Land Department as project no. 2877.
Does Terra Golf Collection have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205835427305. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Terra Golf Collection?
The most recent sale registered with Dubai Land Department was on 14 July 2026 for AED 10,950,000. Across the 16 recorded sales, the average was AED 4,028 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.