photo: takayamotorcity.comUnder constructionTakaya
Developer: Takaya Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 5 Oct 2026 | Sales | Off-plan | Flat · 3 B/R | 156.7 | 1,687 | 2,889,831 | 18,442 | 1,713 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 174.6 | 1,879 | 3,585,857 | 20,538 | 1,908 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 118.65 | 1,277 | 2,526,197 | 21,291 | 1,978 |
| 9 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 118.48 | 1,275 | 2,458,372 | 20,749 | 1,928 |
| 7 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 174.6 | 1,879 | 3,628,356 | 20,781 | 1,931 |
| 7 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 113.25 | 1,219 | 2,400,982 | 21,201 | 1,970 |
| 7 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 174.6 | 1,879 | 3,614,009 | 20,699 | 1,923 |
| 7 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 117.25 | 1,262 | 2,502,719 | 21,345 | 1,983 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 174.6 | 1,879 | 3,697,486 | 21,177 | 1,967 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 111.35 | 1,199 | 2,286,852 | 20,538 | 1,908 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 113.1 | 1,217 | 2,335,765 | 20,652 | 1,919 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 116.91 | 1,258 | 2,401,046 | 20,538 | 1,908 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 174.6 | 1,879 | 3,670,094 | 21,020 | 1,953 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 111.35 | 1,199 | 2,316,200 | 20,801 | 1,932 |
| 6 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 151.33 | 1,629 | 2,840,819.04 | 18,772 | 1,744 |
Takaya: common questions
Is Takaya delayed?
It is behind plan. Construction was 15.62% complete at the last DLD inspection on 5 August 2026, while its registered timeline (planned completion 31 December 2027) would expect about 59% by then.
When is the handover of Takaya?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Takaya is built?
Construction was 15.62% complete at the last DLD inspection on 5 August 2026, as published by Dubai Land Department.
Where is Takaya located?
Takaya is in Motor City, Dubai.
Who is the developer of Takaya?
Takaya is developed by Takaya Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3112.
Does Takaya have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582125637901. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Takaya?
The most recent sale registered with Dubai Land Department was on 5 October 2026 for AED 2,889,831. Across the 80 recorded sales, the average was AED 1,850 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.