photo: symbolic.aeUnder constructionSymbolic Zen Residences
Developer: Moizziyah Developers L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 23 Oct 2026 | Sales | Off-plan | Shop · NA | 37.69 | 406 | 1,400,000 | 37,145 | 3,451 |
| 21 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 142.74 | 1,536 | 2,124,400 | 14,883 | 1,383 |
| 21 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 125.51 | 1,351 | 2,010,000 | 16,015 | 1,488 |
| 13 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 131.22 | 1,412 | 2,106,000 | 16,049 | 1,491 |
| 13 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 136.84 | 1,473 | 2,065,140 | 15,092 | 1,402 |
| 11 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 131.22 | 1,412 | 2,010,000 | 15,318 | 1,423 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 136.84 | 1,473 | 2,007,840 | 14,673 | 1,363 |
| 13 May 2026 | Sales | Off-plan | Flat · 2 B/R | 131.24 | 1,413 | 2,050,000 | 15,620 | 1,451 |
| 13 May 2026 | Sales | Off-plan | Flat · 2 B/R | 125.51 | 1,351 | 1,881,600 | 14,992 | 1,393 |
| 21 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 131.22 | 1,412 | 2,035,200 | 15,510 | 1,441 |
| 7 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 142.74 | 1,536 | 2,080,500 | 14,575 | 1,354 |
| 16 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 136.84 | 1,473 | 2,088,000 | 15,259 | 1,418 |
| 5 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 131.24 | 1,413 | 2,022,450 | 15,410 | 1,432 |
| 3 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 131.24 | 1,413 | 2,009,000 | 15,308 | 1,422 |
| 3 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 125.51 | 1,351 | 1,901,200 | 15,148 | 1,407 |
Symbolic Zen Residences: common questions
Is Symbolic Zen Residences delayed?
It is behind plan. Construction was 2.12% complete at the last DLD inspection on 17 April 2026, while its registered timeline (planned completion 15 June 2027) would expect about 42% by then.
When is the handover of Symbolic Zen Residences?
The planned completion date registered with Dubai Land Department is 15 June 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Symbolic Zen Residences is built?
Construction was 2.12% complete at the last DLD inspection on 17 April 2026, as published by Dubai Land Department.
Where is Symbolic Zen Residences located?
Symbolic Zen Residences is in Al Furjan, Dubai.
Who is the developer of Symbolic Zen Residences?
Symbolic Zen Residences is developed by Moizziyah Developers L.L.C. It is registered with Dubai Land Department as project no. 3755.
Does Symbolic Zen Residences have an escrow account?
Yes. Dubai Land Department open data lists escrow account 012038842127. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Symbolic Zen Residences?
The most recent sale registered with Dubai Land Department was on 23 October 2026 for AED 1,400,000. Across the 21 recorded sales, the average was AED 1,535 per sq ft.