Sunset Bay Two By Imtiazphoto: imtiaz.aeActive
Progress
70.2%
Handover
~ Feb 2027
Escrow
#1011225608110046

Sunset Bay Two By Imtiaz

#3570 · IMTIAZ REAL ESTATE INVESTMENT & DEVELOPMENT L.L.C · Palm Deira

More from Imtiaz
data last checked 17 Jul 2026

Construction progress

70.2% of construction complete · last inspected by DLD 4 Aug 2026

on pace — ≈2 pts behind the plan as of the last inspection

today
inspected 4 Aug 2026
start 20 Feb 2025 est. finish 20 Feb 2027