Sunset Bay One By Imtiazphoto: imtiaz.aeActive
Progress
78.04%
Handover
~ Dec 2026
Escrow
#1011226743829002

Sunset Bay One By Imtiaz

#3460 · IMTIAZ SUNSET REAL ESTATE DEVELOPMENT L.L.C · Palm Deira · 66 units

More from Imtiaz
declared value 65.0M AED data last checked 12 Sept 2026

G+2P+8Floor+Roof Residential Building. The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

78.04% of construction complete · last inspected by DLD 4 Aug 2026

on pace — ≈2 pts behind the plan as of the last inspection

today
inspected 4 Aug 2026
start 25 Dec 2024 est. finish 25 Dec 2026
Google · this project
4.8
5 reviews