SUNSET BAY FIVE by Imtiazphoto: imtiaz.aeActive
Progress
32.62%
Handover
~ Oct 2027
Escrow
#1011226813396004

SUNSET BAY FIVE by Imtiaz

#3811 · Imtiaz Ug Real Estate Development L.L.C · Palm Deira

More from Imtiaz
data last checked 17 Jul 2026

Construction progress

32.62% of construction complete · last inspected by DLD 9 Jul 2026

on pace — ≈13 pts behind the plan as of the last inspection

today
inspected 9 Jul 2026
start 15 Jun 2025 est. finish 15 Oct 2027