photo: nuriliving.comUnder constructionSukoon by Nuri
DLD developer no. 2320 · NURI REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
1B+G+5+1R
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 25 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 115.55 | 1,244 | 2,473,000 | 21,402 | 1,988 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.17 | 798 | 1,504,000 | 20,278 | 1,884 |
| 5 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 111.81 | 1,204 | 2,426,000 | 21,698 | 2,016 |
| 1 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 79.42 | 855 | 1,683,000 | 21,191 | 1,969 |
| 9 May 2026 | Sales | Off-plan | Flat · 1 B/R | 79.03 | 851 | 1,505,000 | 19,043 | 1,769 |
| 8 May 2026 | Sales | Off-plan | Flat · 1 B/R | 85.62 | 922 | 1,538,000 | 17,963 | 1,669 |
| 7 May 2026 | Sales | Off-plan | Flat · 1 B/R | 106.66 | 1,148 | 1,600,000 | 15,001 | 1,394 |
| 7 May 2026 | Sales | Off-plan | Flat · 1 B/R | 108.62 | 1,169 | 1,661,000 | 15,292 | 1,421 |
| 30 Apr 2026 | Sales | Off-plan | Shop · NA | 42.78 | 460 | 1,650,000 | 38,569 | 3,583 |
| 17 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 88.33 | 951 | 1,698,000 | 19,223 | 1,786 |
| 16 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 79.44 | 855 | 1,690,000 | 21,274 | 1,976 |
| 4 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 74.41 | 801 | 1,529,000 | 20,548 | 1,909 |
| 4 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 74.17 | 798 | 1,515,000 | 20,426 | 1,898 |
| 3 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 75.74 | 815 | 1,469,000 | 19,395 | 1,802 |
| 28 Feb 2026 | Sales | Off-plan | Shop · NA | 63.08 | 679 | 2,375,000 | 37,651 | 3,498 |
Sukoon by Nuri: common questions
Is Sukoon by Nuri delayed?
Not by DLD figures. Construction was 46.77% complete at the last DLD inspection on 30 June 2026, in line with or ahead of its registered timeline (about 70% expected by then, planned completion 31 December 2026).
When is the handover of Sukoon by Nuri?
The planned completion date registered with Dubai Land Department is 31 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Sukoon by Nuri is built?
Construction was 46.77% complete at the last DLD inspection on 30 June 2026, as published by Dubai Land Department.
Where is Sukoon by Nuri located?
Sukoon by Nuri is in Nad Al Shiba First, Dubai.
Who is the developer of Sukoon by Nuri?
Sukoon by Nuri is developed by NURI REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 2320). It is registered with Dubai Land Department as project no. 3753, with 41 units.
Does Sukoon by Nuri have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0800008638002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Sukoon by Nuri?
The most recent sale registered with Dubai Land Department was on 25 July 2026 for AED 2,473,000. Across the 30 recorded sales, the average was AED 2,041 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.