photo: stamndevelopment.comDelayedSTAMN ONE
DLD developer no. 1943 · STAMN REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
G+2P+7+Roof.The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.67 | 459 | 1,042,375 | 24,429 | 2,270 |
| 27 Aug 2026 | Sales | Off-plan | Flat · Studio | 45.15 | 486 | 1,026,292 | 22,731 | 2,112 |
| 11 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 84.85 | 913 | 1,698,661 | 20,020 | 1,860 |
| 20 May 2026 | Sales | Off-plan | Flat · Studio | 71.27 | 767 | 1,175,917 | 16,499 | 1,533 |
| 6 May 2026 | Sales | Off-plan | Flat · Studio | 43.7 | 470 | 1,051,574 | 24,063 | 2,236 |
| 20 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 91.38 | 984 | 1,939,418 | 21,224 | 1,972 |
| 20 Apr 2026 | Sales | Off-plan | Flat · Studio | 42.97 | 463 | 1,161,737 | 27,036 | 2,512 |
| 18 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 124.42 | 1,339 | 2,024,617 | 16,272 | 1,512 |
| 15 Apr 2026 | Sales | Off-plan | Flat · Studio | 42.67 | 459 | 1,093,916 | 25,637 | 2,382 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 124.38 | 1,339 | 2,200,000 | 17,688 | 1,643 |
| 4 Apr 2026 | Sales | Off-plan | Flat · Studio | 42.68 | 459 | 1,117,172 | 26,176 | 2,432 |
| 24 Mar 2026 | Sales | Off-plan | Flat · Studio | 48.84 | 526 | 1,059,156 | 21,686 | 2,015 |
| 16 Mar 2026 | Sales | Off-plan | Flat · Studio | 43.7 | 470 | 1,194,540 | 27,335 | 2,540 |
| 13 Mar 2026 | Sales | Off-plan | Flat · Studio | 42.68 | 459 | 1,089,576 | 25,529 | 2,372 |
| 3 Mar 2026 | Sales | Off-plan | Flat · Studio | 49.41 | 532 | 1,098,955 | 22,242 | 2,066 |
STAMN ONE: common questions
Is STAMN ONE delayed?
It is behind plan. Construction was 42.05% complete at the last DLD inspection on 25 August 2026, while its registered timeline (planned completion 15 October 2026) would expect about 92% by then.
When is the handover of STAMN ONE?
The planned completion date registered with Dubai Land Department is 15 October 2026. Handover usually follows completion; the developer confirms the exact date.
How much of STAMN ONE is built?
Construction was 42.05% complete at the last DLD inspection on 25 August 2026, as published by Dubai Land Department.
Where is STAMN ONE located?
STAMN ONE is in Al Satwa, Dubai.
Who is the developer of STAMN ONE?
STAMN ONE is developed by STAMN REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1943). It is registered with Dubai Land Department as project no. 3243, with 77 units.
Does STAMN ONE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1011226081896003. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in STAMN ONE?
The most recent sale registered with Dubai Land Department was on 21 October 2026 for AED 1,042,375. Across the 23 recorded sales, the average was AED 2,023 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.