Sportz By Danubephoto: danubeproperties.comActive
Progress
68.83%
Handover
Escrow
#1034025563004

Sportz By Danube

#2845 · DANUBE PROPERTIES DEVELOPMENT L.L.C · Al Hebiah Fourth · 1110 units

More from Danube
declared value 463.9M AED data last checked 12 Sept 2026

Building 1 (A):33F+R,Building 2 (B):33F+R,(shared):G+5P+R. Residential , The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

68.83% of construction complete · last inspected by DLD 7 Sept 2026

overdue — planned finish was 30 Mar 2026, still at 68.83%

today
inspected 7 Sept 2026
start 1 Jun 2024 est. finish 30 Mar 2026