South Squarephoto: dubaisouth-projects.aeActive
Progress
2.62%
Handover
~ Jun 2028
Escrow
#1009917095

South Square

#3711 · DUBAI SOUTH PROPERTIES DWC LLC · Madinat Al Mataar

data last checked 17 Jul 2026

Construction progress

2.62% of construction complete · last inspected by DLD 17 Jun 2026

on pace — ≈21 pts behind the plan as of the last inspection

today
inspected 17 Jun 2026
start 30 Oct 2025 est. finish 30 Jun 2028