South Garden Ephoto: wasl.aeActive
Progress
8%
Handover
~ May 2028
Escrow
#0205256550220

South Garden E

#3761 · JAG DEVELOPMENT L.L.C · Jabal Ali First

data last checked 17 Jul 2026

Construction progress

8% of construction complete · last inspected by DLD 7 Sept 2026

on pace — ≈25 pts behind the plan as of the last inspection

today
inspected 7 Sept 2026
start 31 Oct 2025 est. finish 31 May 2028