photo: wasl.aeUnder constructionSouth Garden C
DLD developer no. 1233 · JAG DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 5 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 98.89 | 1,064 | 1,227,000 | 12,408 | 1,153 |
| 28 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 79.69 | 858 | 1,002,560 | 12,581 | 1,169 |
| 16 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 107.12 | 1,153 | 1,437,280 | 13,417 | 1,247 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 120.49 | 1,297 | 1,797,000 | 14,914 | 1,386 |
| 6 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 107.16 | 1,153 | 1,400,000 | 13,065 | 1,214 |
| 25 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 87.7 | 944 | 1,152,000 | 13,136 | 1,220 |
| 2 May 2026 | Sales | Off-plan | Flat · 2 B/R | 114.31 | 1,230 | 1,622,000 | 14,189 | 1,318 |
| 2 May 2026 | Sales | Off-plan | Flat · 2 B/R | 120.7 | 1,299 | 1,733,000 | 14,358 | 1,334 |
| 18 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 171.36 | 1,845 | 2,456,000 | 14,332 | 1,332 |
| 15 Apr 2026 | Sales | Off-plan | Flat · Studio | 40.71 | 438 | 588,000 | 14,444 | 1,342 |
| 18 Mar 2026 | Sales | Off-plan | Flat · 1 B/R | 79.72 | 858 | 1,122,400 | 14,079 | 1,308 |
| 3 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 114.27 | 1,230 | 1,700,000 | 14,877 | 1,382 |
| 24 Feb 2026 | Sales | Off-plan | Flat · Studio | 40.72 | 438 | 670,000 | 16,454 | 1,529 |
| 26 Jan 2026 | Sales | Off-plan | Flat · Studio | 37.08 | 399 | 695,000 | 18,743 | 1,741 |
South Garden C: common questions
Is South Garden C delayed?
It is behind plan. Construction was 16.15% complete at the last DLD inspection on 7 September 2026, while its registered timeline (planned completion 31 December 2027) would expect about 56% by then.
When is the handover of South Garden C?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of South Garden C is built?
Construction was 16.15% complete at the last DLD inspection on 7 September 2026, as published by Dubai Land Department.
Where is South Garden C located?
South Garden C is in Jabal Ali First, Dubai.
Who is the developer of South Garden C?
South Garden C is developed by JAG DEVELOPMENT L.L.C (DLD developer no. 1233). It is registered with Dubai Land Department as project no. 3141.
Does South Garden C have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205256550214. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in South Garden C?
The most recent sale registered with Dubai Land Department was on 5 October 2026 for AED 1,227,000. Across the 14 recorded sales, the average was AED 1,334 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.