South Garden Cphoto: wasl.aeActive
Progress
16.15%
Handover
~ Dec 2027
Escrow
#0205256550214

South Garden C

#3141 · JAG DEVELOPMENT L.L.C · Jabal Ali First

data last checked 17 Jul 2026

Construction progress

16.15% of construction complete · last inspected by DLD 7 Sept 2026

≈40 pts behind the planned pace as of the last inspection

today
inspected 7 Sept 2026
start 1 Jan 2025 est. finish 31 Dec 2027