photo: solproperties.aeUnder constructionSOLARA TOWER DUBAI
DLD developer no. 999 · S O L PROPERTIES DEVELOPMENT L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 21 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 190.48 | 2,050 | 2,935,000 | 15,408 | 1,431 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 263.82 | 2,840 | 9,732,327.25 | 36,890 | 3,427 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 183.78 | 1,978 | 1,480,000 | 8,053 | 748 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 4 B/R | 384.51 | 4,139 | 20,121,220 | 52,330 | 4,862 |
| 29 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 159.73 | 1,719 | 6,096,000 | 38,164 | 3,546 |
| 17 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 253.48 | 2,728 | 10,498,950 | 41,419 | 3,848 |
| 16 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 253.06 | 2,724 | 10,486,080 | 41,437 | 3,850 |
| 15 Jul 2026 | Sales | Off-plan | Flat · 3 B/R | 253.06 | 2,724 | 10,272,360 | 40,593 | 3,771 |
| 29 Jun 2026 | Sales | Off-plan | Flat · 3 B/R | 260.03 | 2,799 | 10,631,000 | 40,884 | 3,798 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 88.55 | 953 | 2,843,555 | 32,112 | 2,983 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 3 B/R | 253.89 | 2,733 | 9,959,740 | 39,229 | 3,644 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 212.55 | 2,288 | 7,204,000 | 33,893 | 3,149 |
| 18 Jun 2026 | Sales | Off-plan | Flat · 3 B/R | 238.12 | 2,563 | 10,679,000 | 44,847 | 4,166 |
| 11 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 195.64 | 2,106 | 7,895,823 | 40,359 | 3,749 |
| 22 May 2026 | Sales | Off-plan | Flat · 2 B/R | 183.78 | 1,978 | 8,979,300 | 48,859 | 4,539 |
SOLARA TOWER DUBAI: common questions
Is SOLARA TOWER DUBAI delayed?
It is behind plan. Construction was 20.73% complete at the last DLD inspection on 30 June 2026, while its registered timeline (planned completion 15 August 2027) would expect about 63% by then.
When is the handover of SOLARA TOWER DUBAI?
The planned completion date registered with Dubai Land Department is 15 August 2027. Handover usually follows completion; the developer confirms the exact date.
How much of SOLARA TOWER DUBAI is built?
Construction was 20.73% complete at the last DLD inspection on 30 June 2026, as published by Dubai Land Department.
Where is SOLARA TOWER DUBAI located?
SOLARA TOWER DUBAI is in Burj Khalifa, Dubai.
Who is the developer of SOLARA TOWER DUBAI?
SOLARA TOWER DUBAI is developed by S O L PROPERTIES DEVELOPMENT L.L.C (DLD developer no. 999). It is registered with Dubai Land Department as project no. 2928.
Does SOLARA TOWER DUBAI have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0204876035503. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in SOLARA TOWER DUBAI?
The most recent sale registered with Dubai Land Department was on 21 October 2026 for AED 2,935,000. Across the 35 recorded sales, the average was AED 3,672 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.