SOL LUXEphoto: solproperties.aeUnder construction

SOL LUXE

DLD project no. 4016 · Trade Center First

Progress
1.99%
DLD inspected 30 Jun 2026
Handover
~ Mar 2029
Est. finish 15 Mar 2029
Escrow
#019500000828
Registered escrow account
Google rating
4.7 ★
7 reviews

DLD developer no. 999 · S O L PROPERTIES DEVELOPMENT L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
1.99% of construction complete · last inspected by DLD 30 Jun 2026

on pace — ≈19 pts behind the plan as of the last inspection

today
inspected 30 Jun 2026
start 15 Oct 2025 est. finish 15 Mar 2029
Google · this project
4.7
7 reviews

Location

SOL LUXE: common questions

Is SOL LUXE delayed?

Not by DLD figures. Construction was 1.99% complete at the last DLD inspection on 30 June 2026, in line with or ahead of its registered timeline (about 21% expected by then, planned completion 15 March 2029).

When is the handover of SOL LUXE?

The planned completion date registered with Dubai Land Department is 15 March 2029. Handover usually follows completion; the developer confirms the exact date.

How much of SOL LUXE is built?

Construction was 1.99% complete at the last DLD inspection on 30 June 2026, as published by Dubai Land Department.

Where is SOL LUXE located?

SOL LUXE is in Trade Center First, Dubai.

Who is the developer of SOL LUXE?

SOL LUXE is developed by S O L PROPERTIES DEVELOPMENT L.L.C (DLD developer no. 999). It is registered with Dubai Land Department as project no. 4016.

Does SOL LUXE have an escrow account?

Yes. Dubai Land Department open data lists escrow account 019500000828. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in SOL LUXE?

The most recent sale registered with Dubai Land Department was on 14 October 2026 for AED 6,440,000. Across the 93 recorded sales, the average was AED 3,624 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.