photo: sobharealty.comUnder constructionDLD developer no. 966 · SOBHA L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Sobha Realty →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Gifts | Off-plan | Flat · 1 B/R | 50.63 | 545 | 544,872.36 | 10,762 | 1,000 |
| 22 Oct 2026 | Sales | Off-plan | Shop · NA | 155.29 | 1,672 | 6,686,120 | 43,056 | 4,000 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 104.6 | 1,126 | 2,246,190 | 21,474 | 1,995 |
| 15 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 104.51 | 1,125 | 2,137,386 | 20,451 | 1,900 |
| 14 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 104.56 | 1,125 | 2,262,215 | 21,636 | 2,010 |
| 3 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 104.61 | 1,126 | 2,212,610 | 21,151 | 1,965 |
| 2 Oct 2026 | Sales | Off-plan | Shop · NA | 105.99 | 1,141 | 4,848,698 | 45,747 | 4,250 |
| 30 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 50.26 | 541 | 1,090,115 | 21,690 | 2,015 |
| 21 Sept 2026 | Sales | Off-plan | Shop · NA | 130.79 | 1,408 | 5,983,193 | 45,747 | 4,250 |
| 18 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 104.47 | 1,125 | 2,310,848 | 22,120 | 2,055 |
| 14 Sept 2026 | Sales | Off-plan | Shop · NA | 189.01 | 2,034 | 8,137,960 | 43,056 | 4,000 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 104.47 | 1,125 | 2,293,980 | 21,958 | 2,040 |
| 8 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 57.1 | 615 | 940,000 | 16,462 | 1,529 |
| 4 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 50.76 | 546 | 1,090,000.44 | 21,474 | 1,995 |
| 3 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 49.78 | 536 | 1,060,943 | 21,313 | 1,980 |
Sobha Solis: common questions
Is Sobha Solis delayed?
It is behind plan. Construction was 17.92% complete at the last DLD inspection on 22 October 2026, while its registered timeline (planned completion 31 December 2028) would expect about 48% by then.
When is the handover of Sobha Solis?
The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Sobha Solis is built?
Construction was 17.92% complete at the last DLD inspection on 22 October 2026, as published by Dubai Land Department.
Where is Sobha Solis located?
Sobha Solis is in Motor City, Dubai.
Who is the developer of Sobha Solis?
Sobha Solis is developed by SOBHA L.L.C (DLD developer no. 966). It is registered with Dubai Land Department as project no. 3334.
Does Sobha Solis have an escrow account?
Yes. Dubai Land Department open data lists escrow account 11423450920005. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Sobha Solis?
The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 6,686,120. Across the 91 recorded sales, the average was AED 2,345 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.