Sobha Orbisphoto: sobharealty.comUnder construction

Sobha Orbis

DLD project no. 3070 · Motor City

Progress
18.2%
DLD inspected 13 Aug 2026
Handover
~ Dec 2028
Est. finish 31 Dec 2028
Escrow
#001640199690701
Registered escrow account
Google rating
4.4 ★
30 reviews

DLD developer no. 966 · SOBHA L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Sobha Realty →
DLDConstruction inspection
18.2% of construction complete · last inspected by DLD 13 Aug 2026

≈30 pts behind the planned pace as of the last inspection

today
inspected 13 Aug 2026
start 1 Jun 2024 est. finish 31 Dec 2028
Google · this project
4.4
30 reviews

Location

Sobha Orbis: common questions

Is Sobha Orbis delayed?

It is behind plan. Construction was 18.2% complete at the last DLD inspection on 13 August 2026, while its registered timeline (planned completion 31 December 2028) would expect about 48% by then.

When is the handover of Sobha Orbis?

The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Sobha Orbis is built?

Construction was 18.2% complete at the last DLD inspection on 13 August 2026, as published by Dubai Land Department.

Where is Sobha Orbis located?

Sobha Orbis is in Motor City, Dubai.

Who is the developer of Sobha Orbis?

Sobha Orbis is developed by SOBHA L.L.C (DLD developer no. 966). It is registered with Dubai Land Department as project no. 3070.

Does Sobha Orbis have an escrow account?

Yes. Dubai Land Department open data lists escrow account 001640199690701. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Sobha Orbis?

The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 5,780,200. Across the 82 recorded sales, the average was AED 2,941 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.