photo: hredevelopment.comDelayed 4 mo.Skyhills III by HRE
DLD developer no. 1669 · HRE REAL ESTATE DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Residential Building UG+G+4P+(10 Residential Floors Tower A + 42 Residential Floors Tower B)+R with Showrooms @ GF
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 32.23 | 347 | 693,913 | 21,530 | 2,000 |
| 27 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 101.73 | 1,095 | 1,835,896 | 18,047 | 1,677 |
| 27 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 101.73 | 1,095 | 1,829,154 | 17,980 | 1,670 |
| 6 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 107.29 | 1,155 | 1,649,083 | 15,370 | 1,428 |
| 17 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 101.73 | 1,095 | 1,676,847 | 16,483 | 1,531 |
| 11 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 76.16 | 820 | 1,269,994.5 | 16,675 | 1,549 |
| 27 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 115.19 | 1,240 | 1,740,146.35 | 15,107 | 1,403 |
| 22 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 123.17 | 1,326 | 1,861,856.92 | 15,116 | 1,404 |
| 19 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 96.52 | 1,039 | 1,658,606.88 | 17,184 | 1,596 |
| 14 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 76.16 | 820 | 1,391,198 | 18,267 | 1,697 |
| 14 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 69.22 | 745 | 1,288,563.78 | 18,615 | 1,729 |
| 14 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 63.3 | 681 | 1,075,401 | 16,989 | 1,578 |
| 14 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 76.16 | 820 | 1,352,680.52 | 17,761 | 1,650 |
| 14 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 137.56 | 1,481 | 2,019,293.62 | 14,679 | 1,364 |
| 13 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 76.16 | 820 | 1,346,243.6 | 17,677 | 1,642 |
Skyhills III by HRE: common questions
Is Skyhills III by HRE delayed?
Yes. Its planned completion date registered with Dubai Land Department was 1 June 2026, and at the last DLD inspection on 1 September 2026 construction was 75.66% complete.
When is the handover of Skyhills III by HRE?
The planned completion date registered with Dubai Land Department is 1 June 2026. That date has passed and construction is still under way, so confirm the current schedule with the developer.
How much of Skyhills III by HRE is built?
Construction was 75.66% complete at the last DLD inspection on 1 September 2026, as published by Dubai Land Department.
Where is Skyhills III by HRE located?
Skyhills III by HRE is in Jumeirah Village Circle (JVC), Dubai. Dubai Land Department records it under the Al Barsha South Fourth area.
Who is the developer of Skyhills III by HRE?
Skyhills III by HRE is developed by HRE REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1669). It is registered with Dubai Land Department as project no. 3058, with 563 units.
Does Skyhills III by HRE have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0012157179015. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Skyhills III by HRE?
The most recent sale registered with Dubai Land Department was on 2 October 2026 for AED 693,913. Across the 49 recorded sales, the average was AED 1,638 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.