SILVIANA PARK LIVINGphoto: object-1.comActive
Progress
2.67%
Handover
~ Mar 2027
Escrow
#19556888

SILVIANA PARK LIVING

#4216 · OBJ1 REAL ESTATE DEVELOPMENT L.L.C · Jumeirah Village Triangle

More from Object 1
data last checked 17 Jul 2026

Construction progress

2.67% of construction complete · last inspected by DLD 13 Aug 2026

≈52 pts behind the planned pace as of the last inspection

today
inspected 13 Aug 2026
start 15 Nov 2025 est. finish 30 Mar 2027
Google · this project
5.0
1 reviews