Samana Imperial Gardenphoto: samanadevelopers.comActive
Progress
3.7%
Handover
~ Dec 2028
Escrow
#14244039830005

Samana Imperial Garden

#3797 · SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C · Arjan

escrow #14244039830005

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

3.7% of construction complete · last inspected by DLD 19 Jun 2026

on pace — ≈24 pts behind the plan as of the last inspection

today
inspected 19 Jun 2026
start 1 Jul 2025 est. finish 31 Dec 2028