| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 15 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 73.08 | 787 | 969,000 | 13,259 | 1,232 |
| 7 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 95.03 | 1,023 | 1,249,000 | 13,143 | 1,221 |
| 1 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 80.47 | 866 | 1,199,000 | 14,900 | 1,384 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 69.41 | 747 | 1,033,061.67 | 14,883 | 1,383 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 95.03 | 1,023 | 1,372,017.67 | 14,438 | 1,341 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.59 | 835 | 1,224,793.34 | 15,785 | 1,467 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 80.21 | 863 | 1,199,000 | 14,948 | 1,389 |
| 26 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 72.99 | 786 | 969,000 | 13,276 | 1,233 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 61.75 | 665 | 949,000 | 15,368 | 1,428 |
| 24 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 84.02 | 904 | 1,263,173.34 | 15,034 | 1,397 |
| 18 Aug 2026 | Sales | Off-plan | Flat · Studio | 34.12 | 367 | 647,745.34 | 18,984 | 1,764 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 61.75 | 665 | 949,000 | 15,368 | 1,428 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 80.21 | 863 | 1,232,500 | 15,366 | 1,428 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 83.28 | 896 | 1,184,894.12 | 14,228 | 1,322 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 58.32 | 628 | 615,999 | 10,562 | 981 |
Samana Hills South 3: common questions
Is Samana Hills South 3 delayed?
Not by DLD figures. Construction was 4.6% complete at the last DLD inspection on 22 June 2026, in line with or ahead of its registered timeline (about 27% expected by then, planned completion 31 August 2028).
When is the handover of Samana Hills South 3?
The planned completion date registered with Dubai Land Department is 31 August 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Samana Hills South 3 is built?
Construction was 4.6% complete at the last DLD inspection on 22 June 2026, as published by Dubai Land Department.
Where is Samana Hills South 3 located?
Samana Hills South 3 is in Dubai Industrial City, Dubai.
Who is the developer of Samana Hills South 3?
Samana Hills South 3 is developed by SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C (DLD developer no. 1598). It is registered with Dubai Land Department as project no. 4074.
Does Samana Hills South 3 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0405841512105. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Samana Hills South 3?
The most recent sale registered with Dubai Land Department was on 15 October 2026 for AED 969,000. Across the 102 recorded sales, the average was AED 1,464 per sq ft.