photo: samanadevelopers.comUnder constructionDLD developer no. 1598 · SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Samana →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Oct 2026 | Sales | Off-plan | Office · NA | 184.46 | 1,986 | 2,183,492 | 11,837 | 1,100 |
| 28 Oct 2026 | Sales | Off-plan | Office · NA | 142.85 | 1,538 | 1,814,289 | 12,701 | 1,180 |
| 7 Sept 2026 | Sales | Off-plan | Shop · NA | 75.72 | 815 | 2,155,336.72 | 28,465 | 2,644 |
| 12 Aug 2026 | Sales | Off-plan | Shop · NA | 83.19 | 895 | 2,367,967.01 | 28,465 | 2,644 |
| 4 Aug 2026 | Sales | Off-plan | Shop · NA | 69.47 | 748 | 2,214,230.06 | 31,873 | 2,961 |
| 4 Aug 2026 | Sales | Off-plan | Shop · NA | 71.26 | 767 | 2,271,290.67 | 31,873 | 2,961 |
| 17 Jul 2026 | Sales | Off-plan | Shop · NA | 59.91 | 645 | 1,932,818.7 | 32,262 | 2,997 |
| 6 Jul 2026 | Sales | Off-plan | Shop · NA | 127.82 | 1,376 | 3,057,428.95 | 23,920 | 2,222 |
| 3 Jul 2026 | Sales | Off-plan | Shop · NA | 61.37 | 661 | 2,027,644.31 | 33,040 | 3,069 |
| 2 Jul 2026 | Sales | Off-plan | Shop · NA | 81.36 | 876 | 1,525,754.17 | 18,753 | 1,742 |
| 1 Jul 2026 | Sales | Off-plan | Shop · NA | 96.94 | 1,043 | 1,769,233.34 | 18,251 | 1,696 |
| 12 Jun 2026 | Sales | Off-plan | Shop · NA | 68.81 | 741 | 2,219,952.59 | 32,262 | 2,997 |
| 28 Apr 2026 | Sales | Off-plan | Office · NA | 169.02 | 1,819 | 2,050,729 | 12,133 | 1,127 |
| 16 Apr 2026 | Sales | Off-plan | Shop · NA | 58.11 | 625 | 1,874,762.5 | 32,262 | 2,997 |
| 13 Mar 2026 | Sales | Off-plan | Shop · NA | 54.11 | 582 | 1,850,864.89 | 34,206 | 3,178 |
Samana Business Park: common questions
Is Samana Business Park delayed?
It is behind plan. Construction was 12.83% complete at the last DLD inspection on 24 September 2026, while its registered timeline (planned completion 30 September 2028) would expect about 39% by then.
When is the handover of Samana Business Park?
The planned completion date registered with Dubai Land Department is 30 September 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Samana Business Park is built?
Construction was 12.83% complete at the last DLD inspection on 24 September 2026, as published by Dubai Land Department.
Where is Samana Business Park located?
Samana Business Park is in Majan, Dubai.
Who is the developer of Samana Business Park?
Samana Business Park is developed by SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C (DLD developer no. 1598). It is registered with Dubai Land Department as project no. 3812.
Does Samana Business Park have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582185594701. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Samana Business Park?
The most recent sale registered with Dubai Land Department was on 28 October 2026 for AED 2,183,492. Across the 33 recorded sales, the average was AED 1,925 per sq ft.