photo: samanadevelopers.comUnder constructionDLD developer no. 1598 · SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Samana →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Office · NA | 99.2 | 1,068 | 2,518,081.3 | 25,384 | 2,358 |
| 27 Oct 2026 | Sales | Off-plan | Office · NA | 93.56 | 1,007 | 2,374,662.36 | 25,381 | 2,358 |
| 8 Oct 2026 | Sales | Off-plan | Office · NA | 82.45 | 887 | 1,593,212.02 | 19,323 | 1,795 |
| 6 Oct 2026 | Sales | Off-plan | Office · NA | 97.18 | 1,046 | 2,395,255.51 | 24,648 | 2,290 |
| 5 Oct 2026 | Sales | Off-plan | Office · NA | 100.58 | 1,083 | 1,028,508 | 10,226 | 950 |
| 30 Sept 2026 | Sales | Off-plan | Office · NA | 88.45 | 952 | 2,094,457.93 | 23,680 | 2,200 |
| 23 Sept 2026 | Sales | Off-plan | Office · NA | 93.56 | 1,007 | 2,200,054.83 | 23,515 | 2,185 |
| 5 Sept 2026 | Sales | Off-plan | Shop · NA | 171.06 | 1,841 | 5,215,419.57 | 30,489 | 2,833 |
| 3 Sept 2026 | Sales | Off-plan | Office · NA | 95.71 | 1,030 | 2,167,487.56 | 22,646 | 2,104 |
| 14 Aug 2026 | Sales | Off-plan | Shop · NA | 100.83 | 1,085 | 2,752,505.02 | 27,298 | 2,536 |
| 13 Aug 2026 | Sales | Off-plan | Office · NA | 88.45 | 952 | 2,069,110.08 | 23,393 | 2,173 |
| 13 Aug 2026 | Sales | Off-plan | Office · NA | 101.62 | 1,094 | 2,326,617.14 | 22,895 | 2,127 |
| 4 Aug 2026 | Sales | Off-plan | Office · NA | 95.87 | 1,032 | 2,254,615.25 | 23,517 | 2,185 |
| 4 Aug 2026 | Sales | Off-plan | Office · NA | 95.71 | 1,030 | 2,111,526.34 | 22,062 | 2,050 |
| 4 Aug 2026 | Sales | Off-plan | Office · NA | 84.98 | 915 | 1,693,353.58 | 19,926 | 1,851 |
Samana Barari Avenue: common questions
Is Samana Barari Avenue delayed?
It is behind plan. Construction was 6.01% complete at the last DLD inspection on 23 September 2026, while its registered timeline (planned completion 31 October 2028) would expect about 38% by then.
When is the handover of Samana Barari Avenue?
The planned completion date registered with Dubai Land Department is 31 October 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Samana Barari Avenue is built?
Construction was 6.01% complete at the last DLD inspection on 23 September 2026, as published by Dubai Land Department.
Where is Samana Barari Avenue located?
Samana Barari Avenue is in Majan, Dubai.
Who is the developer of Samana Barari Avenue?
Samana Barari Avenue is developed by SAMANA SIGNATURE REAL ESTATE DEVELOPMENTS L.L.C (DLD developer no. 1598). It is registered with Dubai Land Department as project no. 3829.
Does Samana Barari Avenue have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582187009401. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Samana Barari Avenue?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 2,518,081. Across the 85 recorded sales, the average was AED 1,876 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.