Saddlewood Parkphoto: makdevelopers.comActive
Progress
12.45%
Handover
~ Sept 2027
Escrow
#0012485859002

Saddlewood Park

#3889 · Mak Developers L.L.C · Meydan Avenue

data last checked 17 Jul 2026

Construction progress

12.45% of construction complete · last inspected by DLD 24 Aug 2026

≈27 pts behind the planned pace as of the last inspection

today
inspected 24 Aug 2026
start 1 Dec 2025 est. finish 30 Sept 2027