Saba 4photo: gccuae.comUnder construction
Progress
30.35%
DLD inspected 31 Jul 2026
Handover
~ Jun 2027
Est. finish 1 Jun 2027
Escrow
#0205857825702
Registered escrow account
Google rating
3.3 ★
3 reviews

Developer: Saba 4 Fzco

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
30.35% of construction complete · last inspected by DLD 31 Jul 2026

≈45 pts behind the planned pace as of the last inspection

today
inspected 31 Jul 2026
start 1 Feb 2024 est. finish 1 Jun 2027
Google · this project
3.3
3 reviews

Location

Saba 4: common questions

Is Saba 4 delayed?

It is behind plan. Construction was 30.35% complete at the last DLD inspection on 31 July 2026, while its registered timeline (planned completion 1 June 2027) would expect about 75% by then.

When is the handover of Saba 4?

The planned completion date registered with Dubai Land Department is 1 June 2027. Handover usually follows completion; the developer confirms the exact date.

How much of Saba 4 is built?

Construction was 30.35% complete at the last DLD inspection on 31 July 2026, as published by Dubai Land Department.

Where is Saba 4 located?

Saba 4 is in Jumeirah Lakes Towers (JLT), Dubai.

Who is the developer of Saba 4?

Saba 4 is developed by Saba 4 Fzco.

Does Saba 4 have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205857825702. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Saba 4?

The most recent sale registered with Dubai Land Department was on 20 July 2026 for AED 3,054,000. Across the 31 recorded sales, the average was AED 2,607 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.