photo: irth.aeUnder constructionRove Home Marasi Drive
Developer: Irth Signature Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 24 Jul 2026 | Sales | Off-plan | Flat · Studio | 37.02 | 398 | 1,188,379.36 | 32,101 | 2,982 |
| 17 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 55.29 | 595 | 2,180,400 | 39,436 | 3,664 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 97.07 | 1,045 | 2,520,379 | 25,965 | 2,412 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 97.06 | 1,045 | 2,769,908 | 28,538 | 2,651 |
| 2 Apr 2026 | Gifts | Off-plan | Flat · Studio | 36.62 | 394 | 662,501.23 | 18,091 | 1,681 |
| 26 Mar 2026 | Gifts | Off-plan | Flat · 1 B/R | 56.58 | 609 | 2,070,668 | 36,597 | 3,400 |
| 17 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 97.07 | 1,045 | 2,428,177.36 | 25,015 | 2,324 |
| 26 Feb 2026 | Sales | Off-plan | Flat · 2 B/R | 97.07 | 1,045 | 2,335,035 | 24,055 | 2,235 |
| 26 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 56.65 | 610 | 2,044,150.08 | 36,084 | 3,352 |
| 11 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 55.29 | 595 | 2,041,728.4 | 36,928 | 3,431 |
| 30 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 55.29 | 595 | 2,050,000 | 37,077 | 3,445 |
| 30 Jan 2026 | Sales | Off-plan | Flat · Studio | 36.62 | 394 | 1,240,000 | 33,861 | 3,146 |
| 16 Jan 2026 | Sales | Off-plan | Flat · Studio | 31.14 | 335 | 1,050,000 | 33,719 | 3,133 |
| 15 Jan 2026 | Sales | Off-plan | Flat · 1 B/R | 56.58 | 609 | 2,204,571 | 38,964 | 3,620 |
| 13 Jan 2026 | Sales | Off-plan | Flat · Studio | 36.62 | 394 | 1,323,297 | 36,136 | 3,357 |
Rove Home Marasi Drive: common questions
Is Rove Home Marasi Drive delayed?
It is behind plan. Construction was 10% complete at the last DLD inspection on 6 July 2026, while its registered timeline (planned completion 31 August 2027) would expect about 64% by then.
When is the handover of Rove Home Marasi Drive?
The planned completion date registered with Dubai Land Department is 31 August 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Rove Home Marasi Drive is built?
Construction was 10% complete at the last DLD inspection on 6 July 2026, as published by Dubai Land Department.
Where is Rove Home Marasi Drive located?
Rove Home Marasi Drive is in Business Bay, Dubai.
Who is the developer of Rove Home Marasi Drive?
Rove Home Marasi Drive is developed by Irth Signature Development L.L.C. It is registered with Dubai Land Department as project no. 2966.
Does Rove Home Marasi Drive have an escrow account?
Yes. Dubai Land Department open data lists escrow account 1008926493. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Rove Home Marasi Drive?
The most recent sale registered with Dubai Land Department was on 24 July 2026 for AED 1,188,379. Across the 16 recorded sales, the average was AED 3,125 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.