Active
Progress
27.82%
Handover
Escrow
#0205915669005

Rose Gardens 1

#3506 · ROZ REAL ESTATE DEVELOPMENT L.L.C · Al Satwa · 166 units

declared value 72.0M AED data last checked 12 Sept 2026

G+1P+8F+R,Residential Building. The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

27.82% of construction complete · last inspected by DLD 8 Jun 2026

≈64 pts behind the planned pace as of the last inspection

today inspected 8 Jun 2026
start 24 Jan 2025 est. finish 23 Jul 2026