photo: roofdubai.comUnder constructionRoof Comfort
Developer: Roof Enterprises And Development Co. L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 24 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 114.81 | 1,236 | 1,450,800 | 12,637 | 1,174 |
| 22 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 78.53 | 845 | 850,000 | 10,824 | 1,006 |
| 21 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 83.12 | 895 | 920,000 | 11,068 | 1,028 |
| 21 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.17 | 454 | 550,000 | 13,042 | 1,212 |
| 21 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.17 | 454 | 580,000 | 13,754 | 1,278 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.17 | 454 | 550,000 | 13,042 | 1,212 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 46.18 | 497 | 510,000 | 11,044 | 1,026 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 46.18 | 497 | 560,000 | 12,126 | 1,127 |
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.17 | 454 | 610,000 | 14,465 | 1,344 |
| 19 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 79.99 | 861 | 965,000 | 12,064 | 1,121 |
| 16 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.17 | 454 | 550,000 | 13,042 | 1,212 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 83.12 | 895 | 940,000 | 11,309 | 1,051 |
| 16 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 79.99 | 861 | 880,000 | 11,001 | 1,022 |
| 7 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.17 | 454 | 570,000 | 13,517 | 1,256 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 71.46 | 769 | 784,000 | 10,971 | 1,019 |
Roof Comfort: common questions
Is Roof Comfort delayed?
Not by DLD figures. Construction was 50.21% complete at the last DLD inspection on 28 July 2026, in line with or ahead of its registered timeline (about 48% expected by then, planned completion 31 December 2027).
When is the handover of Roof Comfort?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Roof Comfort is built?
Construction was 50.21% complete at the last DLD inspection on 28 July 2026, as published by Dubai Land Department.
Where is Roof Comfort located?
Roof Comfort is in Dubai Land Residence Complex, Dubai.
Who is the developer of Roof Comfort?
Roof Comfort is developed by Roof Enterprises And Development Co. L.L.C. It is registered with Dubai Land Department as project no. 3629.
Does Roof Comfort have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205905203102. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Roof Comfort?
The most recent sale registered with Dubai Land Department was on 24 October 2026 for AED 1,450,800. Across the 25 recorded sales, the average was AED 1,161 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.