Rijas Suitesphoto: dubailand.gov.aeActive
Progress
3.33%
Handover
~ Dec 2028
Escrow
#200822338

Rijas Suites

#3433 · Dusit Rijas Properties L.L.C · Majan

data last checked 17 Jul 2026

Construction progress

3.33% of construction complete · last inspected by DLD 29 Jun 2026

≈35 pts behind the planned pace as of the last inspection

today
inspected 29 Jun 2026
start 26 Nov 2024 est. finish 31 Dec 2028