Repose Residencephoto: saionproperties.comActive
Progress
23.51%
Handover
~ Mar 2027
Escrow
#0012375471002

Repose Residence

#4012 · Saion Real Estate Development L.L.C · Al Furjan

data last checked 17 Jul 2026

Construction progress

23.51% of construction complete · last inspected by DLD 25 Jun 2026

≈31 pts behind the planned pace as of the last inspection

today
inspected 25 Jun 2026
start 1 Aug 2025 est. finish 31 Mar 2027