Reportage Hillsphoto: reportagegroup.comActive
Progress
0.39%
Handover
~ Jun 2028
Escrow
#1009780436

Reportage Hills

#3465 · REPORTAGE PRIME PROPERTIES L.L.C · Al Hebiah Fifth

data last checked 17 Jul 2026

Construction progress

0.39% of construction complete · last inspected by DLD 4 Jun 2026

≈31 pts behind the planned pace as of the last inspection

today
inspected 4 Jun 2026
start 30 Jun 2025 est. finish 30 Jun 2028
Google · this project