Under construction

Renascent Tower

DLD project no. 4173 · Wadi Al Safa 3 · 52 units

Progress
1.94%
DLD inspected 30 Sept 2026
Handover
~ Mar 2028
Est. finish 1 Mar 2028
Escrow
#1011226765774002
Registered escrow account
Google rating
5.0 ★
1 reviews

DLD developer no. 1980 · S A M A R A REAL ESTATE DEVELOPMENT L.L.C

Data last checked 29 Oct 2026

declared value 15.0M AED

B + G+ 5 Floors + Roof

DLDConstruction inspection
1.94% of construction complete · last inspected by DLD 30 Sept 2026

≈37 pts behind the planned pace as of the last inspection

today
inspected 30 Sept 2026
start 1 Nov 2025 est. finish 1 Mar 2028
Google · this project
5.0
1 reviews

Location

Renascent Tower: common questions

Is Renascent Tower delayed?

It is behind plan. Construction was 1.94% complete at the last DLD inspection on 30 September 2026, while its registered timeline (planned completion 1 March 2028) would expect about 39% by then.

When is the handover of Renascent Tower?

The planned completion date registered with Dubai Land Department is 1 March 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Renascent Tower is built?

Construction was 1.94% complete at the last DLD inspection on 30 September 2026, as published by Dubai Land Department.

Where is Renascent Tower located?

Renascent Tower is in Wadi Al Safa 3, Dubai.

Who is the developer of Renascent Tower?

Renascent Tower is developed by S A M A R A REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1980). It is registered with Dubai Land Department as project no. 4173, with 52 units.

Does Renascent Tower have an escrow account?

Yes. Dubai Land Department open data lists escrow account 1011226765774002. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.