| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Flat · Studio | 43.54 | 469 | 795,476.92 | 18,270 | 1,697 |
| 27 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 70.65 | 760 | 1,237,443.29 | 17,515 | 1,627 |
| 27 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 64.16 | 691 | 1,089,623.04 | 16,983 | 1,578 |
| 23 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 74.17 | 798 | 1,335,275.26 | 18,003 | 1,673 |
| 22 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 64.16 | 691 | 1,160,861.73 | 18,093 | 1,681 |
| 16 Oct 2026 | Sales | Off-plan | Flat · Studio | 38.13 | 410 | 732,387.61 | 19,208 | 1,784 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 97.47 | 1,049 | 1,568,612.97 | 16,093 | 1,495 |
| 5 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.5 | 457 | 784,482.54 | 18,458 | 1,715 |
| 30 Sept 2026 | Sales | Off-plan | Flat · Studio | 38.13 | 410 | 820,100.16 | 21,508 | 1,998 |
| 30 Sept 2026 | Sales | Off-plan | Flat · Studio | 42.11 | 453 | 813,852.3 | 19,327 | 1,796 |
| 29 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 134 | 1,442 | 2,099,225.68 | 15,666 | 1,455 |
| 29 Sept 2026 | Sales | Off-plan | Flat · Studio | 42.58 | 458 | 785,964.79 | 18,459 | 1,715 |
| 25 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 97.47 | 1,049 | 1,572,993.27 | 16,138 | 1,499 |
| 25 Sept 2026 | Sales | Off-plan | Flat · Studio | 42.03 | 452 | 786,278.05 | 18,708 | 1,738 |
| 23 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 64.87 | 698 | 1,165,858.09 | 17,972 | 1,670 |
Reef 996: common questions
Is Reef 996 delayed?
It is behind plan. Construction was 0.1% complete at the last DLD inspection on 1 September 2026, while its registered timeline (planned completion 30 September 2028) would expect about 31% by then.
When is the handover of Reef 996?
The planned completion date registered with Dubai Land Department is 30 September 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Reef 996 is built?
Construction was 0.1% complete at the last DLD inspection on 1 September 2026, as published by Dubai Land Department.
Where is Reef 996 located?
Reef 996 is in Dubai Production City, Dubai.
Who is the developer of Reef 996?
Reef 996 is developed by REEF LUXURY DEVELOPMENT L.L.C (DLD developer no. 1944). It is registered with Dubai Land Department as project no. 4062.
Does Reef 996 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 19543036. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Reef 996?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 795,477. Across the 236 recorded sales, the average was AED 1,637 per sq ft.