Redwood Park Phase2photo: jumeirahgolf-estates.comFinished
Progress
100%
Handover
~ Dec 2017
Escrow
#019000027488

Redwood Park Phase2

#1770 · Jumeirah Golf Estates L.L.C · Jumeirah Golf

escrow #019000027488

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

100% of construction complete · last inspected by DLD 18 Dec 2017
inspected 18 Dec 2017
start 9 Jun 2016 est. finish 7 Sept 2017