Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 8 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 84.06 | 905 | 1,050,000 | 12,491 | 1,160 |
| 3 Sept 2026 | Sales | Off-plan | Shop · NA | 104.79 | 1,128 | 3,384,000 | 32,293 | 3,000 |
| 3 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 86.29 | 929 | 1,080,000 | 12,516 | 1,163 |
| 25 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 86.29 | 929 | 1,100,000 | 12,748 | 1,184 |
| 24 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 80.78 | 870 | 1,050,000 | 12,998 | 1,208 |
| 24 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 86.29 | 929 | 1,050,000 | 12,168 | 1,130 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 86.29 | 929 | 1,050,000 | 12,168 | 1,130 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 86.29 | 929 | 1,050,000 | 12,168 | 1,130 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 84.06 | 905 | 1,096,825.35 | 13,048 | 1,212 |
| 6 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 84.06 | 905 | 1,102,536 | 13,116 | 1,219 |
| 28 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 84.06 | 905 | 1,078,477.29 | 12,830 | 1,192 |
| 21 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 80.78 | 870 | 1,050,000 | 12,998 | 1,208 |
| 13 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 86.29 | 929 | 1,050,000 | 12,168 | 1,130 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 84.06 | 905 | 1,050,000 | 12,491 | 1,160 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 80.7 | 869 | 1,051,808 | 13,034 | 1,211 |
Rabdan Gates: common questions
Is Rabdan Gates delayed?
It is behind plan. Construction was 1.08% complete at the last DLD inspection on 23 April 2026, while its registered timeline (planned completion 30 June 2028) would expect about 29% by then.
When is the handover of Rabdan Gates?
The planned completion date registered with Dubai Land Department is 30 June 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Rabdan Gates is built?
Construction was 1.08% complete at the last DLD inspection on 23 April 2026, as published by Dubai Land Department.
Where is Rabdan Gates located?
Rabdan Gates is in Majan, Dubai.
Who is the developer of Rabdan Gates?
Rabdan Gates is developed by RABDAN REAL ESTATE DEVELOPMENT L.L.C (DLD developer no. 1533). It is registered with Dubai Land Department as project no. 3587.
Does Rabdan Gates have an escrow account?
Yes. Dubai Land Department open data lists escrow account 3001748107000. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Rabdan Gates?
The most recent sale registered with Dubai Land Department was on 8 October 2026 for AED 1,050,000. Across the 52 recorded sales, the average was AED 1,319 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.