photo: rovehotels.comUnder constructionR Home MH
DLD developer no. 2349 · BUKADRA DEVELOPMENT L.L.C
Data last checked 29 Oct 2026
Residential Building G+3P+20+R floors
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 11 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 87.59 | 943 | 2,480,000 | 28,314 | 2,630 |
| 11 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 87.49 | 942 | 2,504,000 | 28,620 | 2,659 |
| 9 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 56.63 | 610 | 1,583,000 | 27,953 | 2,597 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 57.32 | 617 | 1,681,000 | 29,327 | 2,725 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 87.59 | 943 | 2,522,000 | 28,793 | 2,675 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 55.03 | 592 | 1,557,000 | 28,294 | 2,629 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 87.59 | 943 | 2,509,000 | 28,645 | 2,661 |
| 4 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 55.03 | 592 | 1,547,000 | 28,112 | 2,612 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 54.65 | 588 | 1,554,000 | 28,435 | 2,642 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 95.13 | 1,024 | 2,492,000 | 26,196 | 2,434 |
| 24 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 56.63 | 610 | 1,621,000 | 28,624 | 2,659 |
| 6 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 108.92 | 1,172 | 2,651,000 | 24,339 | 2,261 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 55.03 | 592 | 1,565,000 | 28,439 | 2,642 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 104.55 | 1,125 | 2,556,000 | 24,448 | 2,271 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 58.2 | 626 | 1,586,000 | 27,251 | 2,532 |
R Home MH: common questions
Is R Home MH delayed?
Not by DLD figures. Construction was 1.78% complete at the last DLD inspection on 21 October 2026, in line with or ahead of its registered timeline (about 16% expected by then, planned completion 31 August 2029).
When is the handover of R Home MH?
The planned completion date registered with Dubai Land Department is 31 August 2029. Handover usually follows completion; the developer confirms the exact date.
How much of R Home MH is built?
Construction was 1.78% complete at the last DLD inspection on 21 October 2026, as published by Dubai Land Department.
Where is R Home MH located?
R Home MH is in Horizon, Dubai. Dubai Land Department records it under the Bukadra area.
Who is the developer of R Home MH?
R Home MH is developed by BUKADRA DEVELOPMENT L.L.C (DLD developer no. 2349). It is registered with Dubai Land Department as project no. 4214, with 190 units.
Does R Home MH have an escrow account?
Yes. Dubai Land Department open data lists escrow account 14373766920002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in R Home MH?
The most recent sale registered with Dubai Land Department was on 11 October 2026 for AED 2,480,000. Across the 52 recorded sales, the average was AED 2,526 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.