photo: aysdevelopers.aeUnder constructionQ GARDENS ALIYA
DLD developer no. 1269 · A Y S PROPERTY DEVELOPMENT
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 74.49 | 802 | 842,323.1 | 11,308 | 1,051 |
| 27 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 72.35 | 779 | 850,000 | 11,748 | 1,091 |
| 13 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 75.44 | 812 | 805,016.95 | 10,671 | 991 |
| 2 Jul 2026 | Sales | Off-plan | Flat · Studio | 37.98 | 409 | 548,485.23 | 14,441 | 1,342 |
| 1 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 72.35 | 779 | 1,200,000 | 16,586 | 1,541 |
| 26 Jun 2026 | Sales | Off-plan | Flat · Studio | 42.22 | 454 | 538,501.2 | 12,755 | 1,185 |
| 23 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.48 | 802 | 921,650.27 | 12,374 | 1,150 |
| 16 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 75.25 | 810 | 860,429.41 | 11,434 | 1,062 |
| 16 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.48 | 802 | 823,367.57 | 11,055 | 1,027 |
| 16 Jun 2026 | Sales | Off-plan | Flat · Studio | 37.98 | 409 | 471,563.89 | 12,416 | 1,153 |
| 3 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 74.46 | 801 | 849,146.17 | 11,404 | 1,059 |
| 8 May 2026 | Sales | Off-plan | Flat · 1 B/R | 72.35 | 779 | 901,318.44 | 12,458 | 1,157 |
| 4 May 2026 | Sales | Off-plan | Flat · Studio | 38.03 | 409 | 522,262.5 | 13,733 | 1,276 |
| 1 May 2026 | Sales | Off-plan | Flat · Studio | 38.03 | 409 | 546,960 | 14,382 | 1,336 |
| 1 May 2026 | Sales | Off-plan | Flat · 1 B/R | 72.35 | 779 | 825,000 | 11,403 | 1,059 |
Q GARDENS ALIYA: common questions
Is Q GARDENS ALIYA delayed?
It is behind plan. Construction was 7.7% complete at the last DLD inspection on 5 July 2026, while its registered timeline (planned completion 30 June 2027) would expect about 64% by then.
When is the handover of Q GARDENS ALIYA?
The planned completion date registered with Dubai Land Department is 30 June 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Q GARDENS ALIYA is built?
Construction was 7.7% complete at the last DLD inspection on 5 July 2026, as published by Dubai Land Department.
Where is Q GARDENS ALIYA located?
Q GARDENS ALIYA is in Jumeirah Village Circle (JVC), Dubai.
Who is the developer of Q GARDENS ALIYA?
Q GARDENS ALIYA is developed by A Y S PROPERTY DEVELOPMENT (DLD developer no. 1269). It is registered with Dubai Land Department as project no. 3290.
Does Q GARDENS ALIYA have an escrow account?
Yes. Dubai Land Department open data lists escrow account 19307905. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Q GARDENS ALIYA?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 842,323. Across the 22 recorded sales, the average was AED 1,181 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.