Purvanchal Triana Residencesphoto: purvanchaluae.aeActive
Progress
26.44%
Handover
~ Mar 2027
Escrow
#90030200025591

Purvanchal Triana Residences

#4095 · PURVANCHAL REAL ESTATE DEVELOPERS L.L.C · Al Satwa

data last checked 17 Jul 2026

Construction progress

26.44% of construction complete · last inspected by DLD 3 Aug 2026

≈37 pts behind the planned pace as of the last inspection

today
inspected 3 Aug 2026
start 1 Aug 2025 est. finish 1 Mar 2027