Pier Point 2photo: emaar.comUnder construction

Pier Point 2

DLD project no. 3305 · Madinat Dubai Almelaheyah

Progress
8.48%
DLD inspected 14 May 2026
Handover
~ Oct 2028
Est. finish 31 Oct 2028
Escrow
#0205838083711
Registered escrow account
Google rating
—

DLD developer no. 1275 · MINA RASHID PROPERTIES L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from Emaar →
DLDConstruction inspection
8.48% of construction complete · last inspected by DLD 14 May 2026

on pace — ≈25 pts behind the plan as of the last inspection

today
inspected 14 May 2026
start 22 Feb 2025 est. finish 31 Oct 2028
Google · this project
0 reviews

Pier Point 2: common questions

Is Pier Point 2 delayed?

Not by DLD figures. Construction was 8.48% complete at the last DLD inspection on 14 May 2026, in line with or ahead of its registered timeline (about 33% expected by then, planned completion 31 October 2028).

When is the handover of Pier Point 2?

The planned completion date registered with Dubai Land Department is 31 October 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Pier Point 2 is built?

Construction was 8.48% complete at the last DLD inspection on 14 May 2026, as published by Dubai Land Department.

Where is Pier Point 2 located?

Pier Point 2 is in Madinat Dubai Almelaheyah, Dubai.

Who is the developer of Pier Point 2?

Pier Point 2 is developed by MINA RASHID PROPERTIES L.L.C (DLD developer no. 1275). It is registered with Dubai Land Department as project no. 3305.

Does Pier Point 2 have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0205838083711. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.